Commissioning of the NET Installation – ICS222
We are pleased to announce that today boiler K13 has been commissioned. Together with the modernized boiler K12 and the RMD station, it forms a complete nitrogen oxides reduction installation at the Pruszków Combined Heat and Power Plant.
The scope of the investment included the delivery of a complete flue gas nitrogen oxides reduction system (the so-called DeNOx installation) for boiler No. K12 type WR25M and boiler No. K13 type WR25/12M, along with systems for reagent storage tanks, tanker unloading, and reagent distribution as part of the modernization of the aforementioned boilers, based on the company’s patented NewEcoTube (NET) technology.
As a result of this investment, the Pruszków plant has achieved the following benefits:
- Compliance with nitrogen oxides and carbon monoxide emission limits at the target level of ≤ 300 mg/Nm³
- Low operating costs due to the stratification of the combustion process and the elimination of water injection into the combustion chamber
- High reliability of the installation.
We would like to thank Energo-Koncept for the reliable execution of the mechanical works and ControlTec for preparing and implementing the control system.
Professional cooperation with industry partners enables us to execute projects to the highest standards.