27th Meeting of the Regional Energy Council under the Marshal of the Lubuskie Voivodeship We would like to inform you that on December 1st, 2023, the 27th meeting of the Regional Energy Council under the Marshal of the Lubuskie Voivodeship was held in Zielona Góra. The meeting focused on topics
MOVIDA – Cost-Driving Media in Industrial Operations We are pleased to inform you that on October 24–26, 2023, in Warsaw, ICS participated in the conference “Cost-Generating Utilities in an Industrial Plant” organized by MOVIDA. During the event, the President of ICS, Mr. Dariusz Szewczyk, delivered a presentation entitled: “Determinants and
27th Forum of Polish District Heating Professionals We are pleased to inform you that, as in previous years, ICS participated in the 27th Polish District Heating Forum, held on September 10–13, 2023, in Międzyzdroje. At the Forum, ICS was represented by its President, Mr. Dariusz Szewczyk, who gave a brief
Completion of the 72-hour trial operation of the NewEcotube installation (nitrogen oxide reduction system) on Boiler K2 at the EC1 Unit in Lubin We are pleased to inform you that on March 22nd, 2023, the 72-hour trial operation of the New Ecotube flue gas denitrification system on Boiler K2 at
Completion of the 72-hour trial operation of the NewEcotube installation (nitrogen oxide reduction system) on Boiler K1 at the EC1 Unit in Lubin We are pleased to inform you that on March 3rd, 2023, the 72-hour trial operation of the New Ecotube flue gas denitrification system on Boiler K1 at
Notice of Company Name Change We hereby inform you that on January 11th, 2023, the name of the company was changed from ICS INDUSTRIAL COMBUSTION SYSTEMS Spółka Akcyjna, with its registered office in Poznań, to ICS Industrial Complete Solutions Spółka Akcyjna, also with its registered office in Poznań. On the
Execution of the project, complete delivery of equipment, and supervision of installation and commissioning of the nitrogen oxides (NOx) reduction system in flue gases for boilers K1, K2, K3, and K4 at MPEC Włocławek.
Commissioning of the Upgraded Combustion System for Steam Boilers KP6 and KP7 at the EC3 Unit in Głogów We are pleased to inform you that on December 28th, 2021, the final acceptance and commissioning protocol was signed for the upgraded combustion system of steam boilers KP6 and KP7 at the
We are pleased to announce the completion of project ICS237. As part of the project, a distillery syrup carbonization system was designed and implemented. Its purpose was the preliminary processing of the syrup through drying and partial carbonization in the Drying and Carbonization Chamber (DCC).
Execution of a flue gas nitrogen oxides reduction installation for two boilers (No. K1 and K4) of type WR-25, along with an installation for unloading, storage, and distribution of ammonia water, as well as a combustion process optimization (carbon monoxide reduction) installation for boiler No. K3 type WR-25.