ICS is proud to present the following projects which have been done by ICS team or are under operation in ICS:
- Execution of the project for the modernization of natural gas burners to enable combustion of E gas in boilers No. 2, 3, and 4 at Energetyka Sp. z o.o., Legnica, Poland. Completion: completion: Q4 2025 – ICS278
- Analysis of the technological and economic feasibility of implementing and installing the Zero-Emission Technological Steam Generator, ENERGO-EFEKT Sp. z o.o., Poznan, Poland, completion: Q3 2025 – ICS298
- Development of the conceptual design for a multi-energy boiler house with a capacity of 5 t/h, Kosmepol Sp. z o.o., Kanie, Poland, completion: Q2 2025 – ICS268
- Delivery of a gas-oil burner adapted for the combustion of mine gas with a variable composition, PGNiG TERMIKA Energetyka Przemysłowa S.A., Jastrzebie Zdroj, Poland, completion: Q2 2025 – ICS282
- Delivery of a gas-oil burner adapted for the combustion of mine gas with a variable composition, PGNiG TERMIKA Energetyka Przemysłowa S.A., Jastrzebie Zdroj, Poland, completion: March 2025 – ICS279
- Feasibility analysis of the methane emission reduction and energy efficiency improvement project at the Grodzisk Wielkopolski Denitrification Plant, ORLEN S.A., Grodzisk Wielkopolski, Poland, commissioning: April 2024 – ICS192
- Modernization of boiler K2 at the EC-4 Department in Legnica, Energetyka Sp. z o.o., Legnica, Poland, commissioning: December 2023 – ICS238
- Design of the nitrogen oxides reduction (deNOx) system for 2 grate boilers, K1 and K2, Energetyka Sp. z o.o., Lubin, Poland, commissioning: March 2023 – ICS242
- Adaptation of the existing MPEC Włocławek heat source to emission standards exceeding the requirements of the IED Directive, MPEC Włocławek, Poland, commissioning: March 2022 – ICS185
- Modernization of the combustion system of steam boilers KP6 and KP7 at the EC3 Głogów department, Energetyka Sp. z o.o., Głogów, Poland, commissioning: December 2021 – ICS199
- Turnkey execution of the nitrogen oxides reduction system in flue gases for two WR-25 type boilers (No. K1 and K4), along with the unloading, storage, and distribution system for ammonia water, ZEC Sp. z o.o., Pabianice, Poland, commissioning: December 2021 – ICS200
- Design and supervision of installation and commissioning of the nitrogen oxides (NOx) reduction system in flue gases for boilers K1, K2, K3, K4, and K5 at the EC-2 Combined Heat and Power Plant Department in Polkowice, Energetyka Sp. z o.o., Polkowice, Poland, commissioning: July 2021 – ICS220
- Turnkey execution of the nitrogen oxides reduction system in flue gases for boiler No. K12 (WR25M type) and boiler No. K13 (WR25/12M type), PEC Pruszkow Sp. z o.o., Pruszkow, Poland, commissioning: January 2020 – ICS222
- Comprehensive execution of the nitrogen oxides reduction system in flue gases for the WR25 No. 4 boiler at the Main Heating Plant in PEC Suwalki, PEC Suwalki Sp. z o.o., Poland, commissioning: February 2019 – ICS197
- Modernization of the K4 boiler at the EC-4 Department in Legnica, Energetyka Sp. z o.o., Legnica, Poland, commissioning: August 2018 – ICS207
- Supply of a steam pressure reduction station for the HMG II steam dryer, Energetyka Sp. z o.o., Glogow, Poland, commissioning: March 2018 – ICS196
- Modernization of the K3 boiler at the EC-4 Department in Legnica, Energetyka Sp. z o.o., Legnica, Poland, commissioning: July 2017 – ICS190
- Modernization of the combustion system in the ORG32/80 No. 5 steam boiler at EC-3 Glogow Department, Energetyka Sp. z o.o., Glogow, Poland, commissioning: December 2014 – ICS131
- Technology and market implementation of synthetic and waste gas combustion using a technology based on the modified HiTAC volumetric combustion method, NCBiR, Poland, commissioning: October 2014 –ICS089
- CFD analysis of the combustion process in the ORG-32 No. 5 steam boiler, Energetyka Sp. z o.o., Glogow, Poland, commissioning: August 2013 – ICS104
- HTB-DL-WG, waste gas utilization (burning) system for steam boiler KP6, Energetyka Sp. z o.o., Glogow, Poland, commissioning: August 2013 – ICS103
- Conceptual design, steam superheater as well as steam reduction in debenzoiling and tar heating processes, ZARMEN/Coke Plant Czestochowa NOWA Sp. z o.o., Poland, realization: June 2013 – ICS118
- CFD analysis, combustion system, 152 MW, 300 t/h steel reheating furnace, walking beam type, SSAB Tunnplat AB, Borlange, Sweden, realization: June 2013 – ICS106
- 3D modelling and CFD analysis, laboratory furnace, Nippon Furnace Co., Ltd (NFK), Japan, realization: May 2013 – ICS116
- Feasibility study, gas boiler, combined heat and power plant, Europe, realization: March 2013 – ICS093
- Technical design, PKK steam boilers, Orion Engineered Carbons, Jaslo, Poland, realization: March 2013 – ICS092
- Technical design and deliveries, steam boiler with firing power rate 99 MW, fired by biomass and natural gas in Stalowa Wola Power Plant, Poland, planned commissioning: August 2012 – ICS053
- HTB-DL-WG, waste gas utilization (burning) system for steam boiler KP7, Energetyka Sp. z o.o., Glogow, Poland; commissioning: June 2012 – ICS072
- Technical design, piping of CO2 firefighting installation for Energa Elektrownie Ostroleka S.A., delivery: May 2012 – ICS084
- Conceptual and technological design, two utilization boilers PKK type at Orion Engineered Carbons Sp. z o.o., Jaslo, Poland; delivery: January 2012 – ICS067
- Research and implementation project, boiler fired by 100% biomass fuel delivery: August 2011 – ICS056
- Delivery, nitrogen pressure tank delivery and taking over: July 2011 – ICS060
- HTB-DL, combustion system, 128.76 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning July/August 2010 – ICS019
- HTB-DL-WG, waste gas utilization system, 41.1 MW, Energetyka Sp. z o.o., Glogow, Poland
38 t/h steam boiler, ORG-32/80M type, commissioning 2010 – ICS007
- HTB-DL-WG, waste gas utilization system, 41.1 MW, Energetyka Sp. z o.o., Glogow, Poland
38 t/h steam boiler, ORG-32/80M type, commissioning July 2009 – ICS002
- HTB-DL, combustion system, 128.76 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning August 2008 – ICS003
- HRS-DL, combustion system, 9.25 MW, Ferrostal, Gliwice, Poland
20 t/h steel reheating furnace, walking beam type, commissioning March 2008 – ICS001
- HTB-DL, combustion system, 62.65 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning August 2006 – PL004*
- HRS-DL, combustion system, 11.6 MW, CORUS, Llanwern, United Kingdom
300 t/h pusher furnace, commissioning April 2006 – PL003*
- HRS-Ux, combustion system, 0.22 MW, Poznan University of Technology, Poznan, Poland
Laboratory test furnace, commissioning 2004 – PL018*
- HRS-RT, combustion system, 0.14 MW, CORUS, Ijmuiden, The Netherlands
Laboratory test furnace, commissioning 2004 – PL001*
- HRS-RT, combustion system, 0.14 MW, Royal Institute of Technology, Stockholm, Sweden
Laboratory test furnace, commissioning 2002 – SE002*
- HRS-DS, combustion system, 0.2 MW, Royal Institute of Technology, Stockholm, Sweden
Laboratory test furnace, commissioning 2000 – SE001*
(*) – project was made by ICS team under the VTS AB and the VTS Poland AB name.