ICS is proud to present the following projects which have been done by ICS team or are under operation in ICS:
- HTB-DL-WG, waste gas utilization (burning) system for steam boiler KP6, Energetyka Sp. z o.o., Glogow, Poland, commissioning: August 2013 - ICS103
- Conceptual design, steam superheater as well as steam reduction in debenzoiling and tar heating processes, ZARMEN/Coke Plant Czestochowa NOWA Sp. z o.o., Poland, realization: June 2013 - ICS118
- CFD analysis, combustion system, 152 MW, 300 t/h steel reheating furnace, walking beam type, SSAB Tunnplat AB, Borlange, Sweden, realization: June 2013 - ICS106
- 3D modelling and CFD analysis, laboratory furnace, Nippon Furnace Co., Ltd (NFK), Japan, realization: May 2013 - ICS116
- Feasibility study, gas boiler, combined heat and power plant, Europe, realization: March 2013 - ICS093
- Technical design, PKK steam boilers, Orion Engineered Carbons, Jaslo, Poland, realization: March 2013 - ICS092
- Technical design and deliveries, steam boiler with firing power rate 99 MW, fired by biomass and natural gas in Stalowa Wola Power Plant, Poland, planned commissioning: August 2012 - ICS053
- HTB-DL-WG, waste gas utilization (burning) system for steam boiler KP7, Energetyka Sp. z o.o., Glogow, Poland; commissioning: June 2012 – ICS072
- Technical design, piping of CO2 firefighting installation for Energa Elektrownie Ostroleka S.A., delivery: May 2012 – ICS084
- Conceptual and technological design, two utilization boilers PKK type at Orion Engineered Carbons Sp. z o.o., Jaslo, Poland; delivery: January 2012 – ICS067
- Research and implementation project, boiler fired by 100% biomass fuel delivery: August 2011 – ICS056
- Delivery, nitrogen pressure tank delivery and taking over: July 2011 – ICS060
- HTB-DL, combustion system, 128.76 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning July/August 2010 - ICS019
- HTB-DL-WG, waste gas utilization system, 41.1 MW, Energetyka Sp. z o.o., Glogow, Poland
38 t/h steam boiler, ORG-32/80M type, commissioning 2010 - ICS007
- HTB-DL-WG, waste gas utilization system, 41.1 MW, Energetyka Sp. z o.o., Glogow, Poland
38 t/h steam boiler, ORG-32/80M type, commissioning July 2009 - ICS002
- HTB-DL, combustion system, 128.76 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning August 2008 - ICS003
- HRS-DL, combustion system, 9.25 MW, Ferrostal, Gliwice, Poland
20 t/h steel reheating furnace, walking beam type, commissioning March 2008 - ICS001
- HTB-DL, combustion system, 62.65 MW, SSAB Tunnplat AB, Borlange, Sweden
300 t/h steel reheating furnace, walking beam type, commissioning August 2006 - PL004*
- HRS-DL, combustion system, 11.6 MW, CORUS, Llanwern, United Kingdom
300 t/h pusher furnace, commissioning April 2006 - PL003*
- HRS-Ux, combustion system, 0.22 MW, Poznan University of Technology, Poznan, Poland
Laboratory test furnace, commissioning 2004 - PL018*
- HRS-RT, combustion system, 0.14 MW, CORUS, Ijmuiden, The Netherlands
Laboratory test furnace, commissioning 2004 - PL001*
- HRS-RT, combustion system, 0.14 MW, Royal Institute of Technology, Stockholm, Sweden
Laboratory test furnace, commissioning 2002 - SE002*
- HRS-DS, combustion system, 0.2 MW, Royal Institute of Technology, Stockholm, Sweden
Laboratory test furnace, commissioning 2000 - SE001*
(*) - project was made by ICS team under the VTS AB and the VTS Poland AB name.
|
|
|